Commuter traffic on the Matinkylä–Kivenlahti section started in December 2022.
The final cost estimate for the construction of the second phase of the West Metro project, i.e. the Matinkylä–Kivenlahti section, is EUR 1,042–1,050 million. The forecast is approximately EUR 100 million, i.e. 9%, less than the estimated cost (EUR 1,159 €M) in the project plan that was updated in 2018. In addition, the project’s financing costs were less than half the amount estimated in the project plan, and these savings will also largely be reflected in the metro’s future annual financing costs.
–The most significant reasons behind the project being completed according to the set targets were reliable cost data obtained from the Ruoholahti–Matinkylä project, strictly controlling the overall project and experienced professionals. The situation management model, a.k.a. war room concept, was an important tool for putting the organisation’s competence and knowledge into use. Cost targets cannot be reached if the targets set for the project’s scope, quality and schedule are not achieved. Successful projects are always the result of successful teamwork, stresses Länsimetro Oy’s CFO Matias Johansson.
The project plan that was drawn up in 2012 for the Matinkylä–Kivenlahti section was adjusted and supplemented in 2018, after the completion of the first phase of the West Metro project, i.e. the Ruoholahti–Matinkylä section. Commuter traffic on the first phase began in November 2017. As the outcome of the first phase, up-to-date information was obtained on the technical requirements and actual costs of building the underground metro, and this information was applied in the second phase of the project. In connection with the updated project plan, the cost estimate increased from EUR 801 million to EUR 1 159 million. The main reasons for the cost adjustments included a change in the surface areas of the stations, adjusted construction costs, a change in how the Espoonlahti bus terminal would be implemented, networking of the stations, extension of the Kivenlahti turnaround track, the addition of a firefighting shaft in Finnoo, reinforcing of the client organisation and schedule changes.
Commuter traffic on the Matinkylä–Kivenlahti section started in December
When the project plan was updated, the schedule was also adjusted: the target was set for the project to be completed in 2023. The Matinkylä–Kivenlahti section was opened to the public earlier than planned, on 3 December 2022. The construction contracts for the stations and the rail line wrapped up in May 2022, after which the test runs continued until September.
– Completion of the Matinkylä–Kivenlahti project in accordance with the set cost and schedule targets was possible thanks to the project’s effective operating methods and close co-operation, not to mention the project organisation’s strong competence and experience. The project’s organisational model and operating and management methods were developed at the start of the second phase’s construction, sums up Länsimetro Oy’s CEO, Ville Saksi.
The project comprised the Matinkylä–Kivenlahti section’s 7 kilometres of rail section, 5 metro stations, an underground depot and the construction of park & ride facilities at Kivenlahti, Kaitaa and Finnoo. The Kivenlahti park & ride facility was recently completed and will be opened to the public at the start of April. The full and final costs of the Matinkylä–Kivenlahti section will only be known once all the work included in the project plan is completed.
Länsimetro Oy is the owner of the modern metro infrastructure
Länsimetro Oy has now shifted the focus of its operations from the construction project to duties related to metro infrastructure ownership. Länsimetro Oy’s mission is to take care of the metro infrastructure throughout its life cycle to ensure that it functions well and safely long into the future.
The Helsinki region’s metro line is the backbone of west-east public transport. Länsimetro owns nearly 50% of the Helsinki region’s metro line kilometres: the 21-kilometre rail line section from Ruoholahti in Helsinki to Kivenlahti in Espoo, 13 metro stations, an underground metro depot and all the related technical systems. Länsimetro also owns the infrastructure that serves feeder traffic, for instance, the park & ride facilities and bus terminals. Länsimetro Oy is a limited liability company jointly owned by the cities of Espoo and Helsinki.
The busiest stations on weekdays on Länsimetro’s section in 2022 were Matinkylä (20,700 users/day), Lauttasaari (16,400 users/day) and Tapiola (14,200 users/day) (Source in Finnish https://kaupunkiliikenne.fi/liikennointi/metrolla/metroasemien-kayttajamaarat/ ). In 2022, the metro had 70 million commuters.
Further information
- Ville Saksi, CEO of Länsimetro Oy, tel. +358 (0) 40 823 2086
- Matias Johansson, CFO of Länsimetro Oy, tel. +358 (0) 40 590 0313
- Marianne Partanen, Communications Manager, Länsimetro Oy, tel. +358 (0) 43 825 9607